Explanation on the Delay of Acceptance of Environmental Assessment for Hangzhou Zhijiang’s "4000 Tons New Industrial Sealing Materials production facilities"

Report date:2019-06-03Reading times: 289

Our company completed the construction of supporting environmental protection facilities on December 30, 2018, according to the construction plan of "4000 tons of new industrial sealing materials per year" (EIA approval: Dajiang East Ring Approval [2018] No. 3), and entered the commissioning stage on January 2, 2019. According to the plan, the commissioning time ranged from January 16, 2019 to April 15, 2019. The debugging time is from April 16, 2019 to January 15, 2020.


    

    